The Middelgrunden wind farm stands on the shoal Middelgrunden, between shipping lanes in the Øresund, 3.5 km outside Copenhagen, Denmark. When it was built in 2000, it was the world's largest offshore farm, with 20 turbines (2 MW Bonus each) and a capacity of 40 MW. The farm delivers about 4% of the power for Copenhagen.[1]

In 1996, the project was initiated by the Copenhagen Environment and Energy Office (CEEO) after Middelgrunden had been listed as a potential site in the Danish Action Plan for Offshore Wind. Together with the CEEO a group of local people formed the Middelgrunden Wind Turbine Cooperative and established a cooperation with Copenhagen Energy, the local electric utility. The proposed location was initially opposed by the Danish Society for Nature Conservation, but this decision was later changed. Concrete gravity base foundations were chosen as the cheapest option.[2]

This project is an example for community wind energy. It is 50% owned by the 10,000 investors in the Middelgrunden Wind Turbine Cooperative, and 50% by the municipal utility company.[3] It is clearly visible from the capital of Denmark.

Gallery

  • Aerial view on landing at Copenhagen Airport on an overcast day.
    Aerial view on landing at Copenhagen Airport on an overcast day.
  • Wind often flows briskly and smoothly over water since there are no obstructions, which is why the location was chosen. The large and slow turning turbines of this offshore wind farm near Copenhagen take advantage of the moderate yet constant breezes at this location. While the wind at this location is not strong it is very consistent, with the turbines generating substantial power over 97 percent of the time.
    Wind often flows briskly and smoothly over water since there are no obstructions, which is why the location was chosen. The large and slow turning turbines of this offshore wind farm near Copenhagen take advantage of the moderate yet constant breezes at this location. While the wind at this location is not strong it is very consistent, with the turbines generating substantial power over 97 percent of the time.

See also

References

  1. ^ "Environmental Capital of Europe". Copenhagen, Environmental Capital of Europe. Archived from the original on 2007-07-06. Retrieved 2009-01-05.
  2. ^ Larsen, Jens H. The World´s largest off-shore windfarm, Middelgrunden 40MW Copenhagen Environment and Energy Office (CEEO), 2001. Retrieved: 19 November 2010.
  3. ^ Hans Christian Sørensen; Lars Kjeld Hansen; Jens H. Mølgaard Larsen (2002). "Middelgrunden 40 MW offshore wind farm Denmark: Lessons Learned" (PDF). SPOK Consult. Archived from the original (PDF) on 2006-08-20. Retrieved 2007-06-21.

External links

  • Middelgrunden Wind Turbine Cooperative (English page)
  • Middelgrunden at 4C
  • LORC Knowledge - Datasheet for Middelgrunden Offshore Wind Farm
  • Middelgrunden at PowerTechnology
  • TV documentary, in Danish
  • v
  • t
  • e
Wind power
Wind powerWind farmsWind turbinesWind power industryManufacturersConcepts
  • icon Wind power portal
  • Category
  • Commons
  • Additional portals:
  • Renewable energy
  • Energy